Software Design and Project Management: Principles, Modularity, Estimation and Scheduling
UNIT III — Software Design & Project Management
1. Software Design
Software design transforms requirements into a blueprint for implementation.
It describes:
- Architecture
- Components
- Interfaces
- Data
- Algorithms
- Relationships between modules
2. Design Fundamentals
Important design concepts include:
1. Abstraction
Represent essential features while hiding unnecessary details.
2. Modularity
Divide software into smaller independent modules.
3. Information Hiding
Hide internal implementation details from other modules.
4. Refinement
Move from a high-level solution to detailed design.
5. Separation of Concerns
Divide the system into parts dealing with different responsibilities.
6. Reusability
Design components so they can be reused.
7. Simplicity
Avoid unnecessary complexity.
3. Effective Modular Design
Modularity means dividing software into independent modules.
Example:
Banking System
|
┌──────────┼──────────┐
↓ ↓ ↓
Login Account Transaction
ManagementAdvantages
- Easier testing.
- Easier maintenance.
- Easier debugging.
- Supports parallel development.
- Promotes reuse.
A good modular design should have:
High cohesion + Low coupling
4. Design Representations
Design can be represented using:
- Flowcharts
- Structure charts
- UML diagrams
- Data-flow diagrams
- Pseudocode
- Decision tables
- Decision trees
- Architecture diagrams
- Class diagrams
5. Architectural Design
Architectural design defines the overall structure of the software system.
It identifies:
- Major components
- Relationships
- Communication between components
- Data organization
Example:
User Interface
↓
Business Logic
↓
Data Access
↓
DatabaseCommon architectural styles
- Layered architecture
- Client-server
- Repository
- Pipe-and-filter
- MVC
6. Procedural Design
Procedural design describes the processing logic and algorithms of the system.
It focuses on:
- Sequence of operations
- Conditions
- Loops
- Data processing
- Algorithms
Common representations
- Flowcharts
- Pseudocode
- Decision tables
- Decision trees
7. Data-Directed Design
Data-directed design organizes software around the data structures and data flow.
The design begins by identifying:
- Data objects
- Data relationships
- Data transformations
It is useful in applications where data processing is central.
8. Real-Time Design
Real-time systems must respond to events within specified time constraints.
Examples
- Air traffic control
- Medical monitoring
- Industrial control
- Automobile control systems
Important concerns
- Timing constraints
- Events
- Concurrency
- Interrupts
- Synchronization
- Reliability
Types
Hard real-time: Missing a deadline can cause system failure.
Soft real-time: Missing an occasional deadline reduces performance but does not necessarily cause catastrophic failure.
9. Object-Oriented Design
Object-oriented design represents a system as a collection of objects/classes.
Important concepts
Class: Blueprint for objects.
Object: Instance of a class.
Encapsulation: Combining data and methods.
Inheritance: Creating a new class from an existing class.
Polymorphism: Same interface can have different implementations.
Abstraction: Showing essential features and hiding unnecessary details.
10. Coupling
Coupling measures the degree of dependency between modules.
Principle
Low coupling is desirable.
Types from stronger to weaker coupling
- Content coupling
- Common coupling
- External coupling
- Control coupling
- Stamp coupling
- Data coupling
Data coupling
Modules communicate by passing only required data.
It is generally preferred.
11. Cohesion
Cohesion measures how closely related the responsibilities within a module are.
Principle
High cohesion is desirable.
Types from weakest to strongest
- Coincidental
- Logical
- Temporal
- Procedural
- Communicational
- Sequential
- Functional
Ideal design
High Cohesion
+
Low Coupling
↓
Better Software Design12. Coupling vs Cohesion
| Coupling | Cohesion |
|---|---|
| Relationship between modules | Relationship within a module |
| Should be low | Should be high |
| Measures dependency | Measures functional strength |
| Low coupling is desirable | High cohesion is desirable |
13. Software Metrics
A software metric is a quantitative measure of a software product, process or project.
Categories
1. Product metrics
Measure characteristics of software.
Examples:
- LOC
- Complexity
- Number of defects
2. Process metrics
Measure development process.
Examples:
- Defect removal efficiency
- Development time
3. Project metrics
Measure project characteristics.
Examples:
- Cost
- Effort
- Schedule
- Productivity
14. Project Management
Software project management involves planning, organizing and controlling resources to achieve project objectives.
A common framework is:
People
↓
Product
↓
Process
↓
ProjectPeople
People are the most important resource in software development.
Roles include:
- Project manager
- Software engineers
- Designers
- Testers
- Customers
- Users
Good communication and teamwork are essential.
Product
Before development, the project manager must understand:
- Product scope
- Objectives
- Requirements
- Constraints
- Expected quality
Process
Process defines how software will be developed.
Examples:
- Waterfall
- Spiral
- Agile
- Iterative development
Project
Project management includes:
- Estimation
- Scheduling
- Risk management
- Resource allocation
- Monitoring
- Quality management
15. Software Project Estimation
Estimation predicts:
- Effort
- Cost
- Development time
- Resources
- Software size
16. LOC-Based Estimation
LOC = Lines of Code
If estimated program size is known, effort can be estimated using an empirical formula.
Example:
If productivity = 500 LOC/person-month and estimated size = 5000 LOC:
Effort = 5000 / 500 = 10 person-months
Advantages
- Simple.
- Easy to understand.
Disadvantages
- Depends on programming language.
- Difficult to estimate LOC before design.
- Does not directly measure functionality.
17. Function Point Estimation
Function Point (FP) measures software size based on functionality provided to users, rather than lines of code.
Five components are considered:
- External Inputs (EI)
- External Outputs (EO)
- External Inquiries (EQ)
- Internal Logical Files (ILF)
- External Interface Files (EIF)
Basic formula
FP = UFP × VAF
Where:
- UFP = Unadjusted Function Points
- VAF = Value Adjustment Factor
Typically:
VAF = 0.65 + 0.01 × ΣFi
where Fi represents the general system characteristics.
Advantages
- Language independent.
- Can estimate early.
- Based on user functionality.
Disadvantages
- Some subjectivity.
- Requires experience.
- More complicated than LOC.
18. Empirical Estimation
Empirical estimation uses mathematical models derived from historical project data.
General form:
Effort = a(Size)b
Where:
- a, b are constants.
- Size may be measured in KLOC or another unit.
Examples:
- COCOMO
- Regression-based models
19. COCOMO Model
COCOMO = Constructive Cost Model
Developed by Barry Boehm.
It estimates software:
- Effort
- Development time
- Cost
Basic COCOMO equation
E = a(KLOC)b
where:
- E = effort in person-months
- KLOC = thousand lines of code
- a, b = constants
Development time:
D = c(E)d
where:
- D = development time in months
- c, d = constants
Average staffing:
Staff = Effort / Development Time
COCOMO Project Modes
1. Organic
- Small/simple projects
- Experienced team
- Familiar environment
2. Semi-detached
- Medium-size projects
- Mixed team experience
- Moderate complexity
3. Embedded
- Complex systems
- Tight hardware/software constraints
- Strong operational constraints
Basic COCOMO coefficients
| Mode | a | b | c | d |
|---|---|---|---|---|
| Organic | 2.4 | 1.05 | 2.5 | 0.38 |
| Semi-detached | 3.0 | 1.12 | 2.5 | 0.35 |
| Embedded | 3.6 | 1.20 | 2.5 | 0.32 |
Example
Suppose an organic project is estimated at 10 KLOC.
E = 2.4(10)1.05
Approximately:
E ≈ 26.4 person-months
Then:
D = 2.5(E)0.38
Approximately:
D ≈ 8.7 months
Average team size:
26.4 / 8.7 ≈ 3
So approximately 3 people would be required on average.
20. Project Scheduling
Project scheduling determines:
- What activities must be performed.
- When activities start/end.
- Who performs them.
- Dependencies between activities.
- Project completion date.
Common scheduling techniques
1. Gantt Chart
A Gantt chart represents activities against time.
Task Week 1 2 3 4 5 6
Requirements ████
Design ██████
Coding █████████
Testing █████
Deployment ██Advantages
- Easy to understand.
- Shows progress.
- Shows start/end dates.
21. PERT
PERT = Program Evaluation and Review Technique
Used when activity durations are uncertain.
Three time estimates are used:
- Optimistic time O
- Most likely time M
- Pessimistic time P
Expected time:
TE = (O + 4M + P) / 6
Example:
If:
O = 2, M = 4, P = 8
Then:
TE = (2 + 4(4) + 8) / 6 = 26 / 6 = 4.33
So expected duration is approximately 4.33 units of time.
22. CPM
CPM = Critical Path Method
CPM identifies the critical path, i.e. the longest path through a project network.
Activities on the critical path have approximately zero total float.
Why is critical path important?
Delay in a critical-path activity can delay the entire project.